Problems Identified

Concentric AB

Issues Identified



- Supplier Issues
* Problem primarily with Chinese manufacturer from West of China
* Quality Issues and Inability to meet product demand and date
* Scheduling vs. Shipping

- Customers Delays resulting in Lost Orders/Lost of Revenue
* Loss Orders (Cancellations)
* Company Reputation suffers
- Intra Company Challenges
* Headquarters vs. Hof Plant
* Rockford, US vs. Hof, Germany
* Internally between Hof Purchasing and Hof Production
- Product Diversification
* Over 300 variations of Power Packs
* Customer requirement/Plant specialty
- Ordering Process
* Complex and time consuming for approximately 20% (Single Orders)
* Confirmation to customer is done manually and must be reconciled with forecast
* Priority customers are often expedited